Recology

Expansion to Recology's Existing Transfer Center
  • Recology_11.14.18
  • West Wing Illustration
  • Construction Photo 2
  • Recology2
Location
San Francisco
Completion
2018
Schedule
13 months
Contract
$18 million
Architect
Brick LLP
Owner
Recology

Project Summary

The West Wing at Recology’s San Francisco’s site is a 14,500 SF building that Nibbi constructed to the west of the compost, recycling, and landfill collection company’s existing transfer station. The buildings are joined along the western wall of the transfer station. The West Wing serves as a tipping and load out area for the organic material collected from the city of San Francisco.