START DATE				April 2002
COMPLETION DATE				June 2003
CONTRACT				$13,836,499	
ARCHITECT				Kaplan, McLaughlin & Diaz Architects
OWNER					City & County of San Francisco

Nibbi Brothers was the successful bidder on the bid package for the concrete superstructure.  Additional scope includes all interior and exterior shotcrete wallsThe new jail will contain 384 cells and will replace the old jail.  Also included is the Administration Building and a housing core of offices, maintenance rooms, etc.

Nibbi Brothers constructed the cells for the project using Outinord tunnel forms, a system that is projected to save three months off the original project schedule.