usps—3rd floor infill
LOCATION: 		Oakland, CA
BUDGET: 			$2,800,000
START DATE: 		October 2007
COMPLETION DATE: 	September 2008
CONSTRUCTION MANAGER: 	Parsons
OWNER: 			United States Post Office

Building of the 3rd floor of existing distribution center. The 20,000 SF space was created by demolishing an existing conveyance system. Scope of work also include infilling the new floor area, with structural steel, metal deck and a concrete floor. We will also install all mechanical and electrical systems, flooring and finishes.